Most small teams finish their first risk assessment with a long register and a vague sense that "we'll sort the red ones". The risk treatment plan is where that turns into work: who does what, by when, and what risk is left afterwards.

This guide covers what to put in the plan, how to size it for a small team, who accepts the risk that is left, how it links to the Statement of Applicability, and how to keep it current between audits.

The basic sequence

The standard is read to set out a short sequence for risk treatment. For each risk, you usually:

  1. Choose a treatment option.
  2. Decide the controls you need to carry it out.
  3. Compare those controls with Annex A, so nothing obvious is missed. That comparison produces your Statement of Applicability.
  4. Write a risk treatment plan.
  5. Get the risk owners' approval of the plan and their acceptance of the residual risk.

Then carry out the plan and keep a record of the results. A plan that sits in a folder and never changes shows nothing.

The four options

Option What it means Small-team example
Reduce Add or improve controls so the risk is lower Turn on multi-factor sign-in for every admin account
Avoid Stop the activity that causes the risk Retire the old file server instead of patching it
Share Pass part of the risk to someone else Cyber insurance, or a supplier with stronger controls
Accept Knowingly keep the risk as it is A low risk that would cost more to treat than it could cost you

Most treatments are "reduce". "Accept" is a valid choice, not a failure, as long as the risk owner makes it on purpose and the record says why. Sharing a risk does not hand it over: you still own it.

Sizing the plan for a small team

A small team has a few people and a lot of other work. The plan has to fit that.

  • Treat what is above your acceptance level. If your method says scores of 10 or less are acceptable, those risks need an "accept" decision, not an action list.
  • Break each treatment into actions small enough to finish. "Improve access control" never closes. "Remove shared admin logins from the firewall" does.
  • One owner per action, with a date. Not a team, not "IT". A person.
  • Plan shared actions once. If multi-factor sign-in treats five risks, it is one action linked to five risks, not five copies that drift apart.
  • Spread the dates. Ten actions due on the same day before the audit is a plan for missing ten dates.

Residual risk, and who accepts it

Residual risk is the risk that is left once the treatment is in place. Score it the same way you scored the original risk.

The risk owner accepts the residual risk. That is the person accountable for the risk, usually the person who runs the process or system. It is not whoever happened to edit the spreadsheet. If the residual score is still above your acceptance level, top management should agree to it in writing, with the reason.

Acceptance is a decision with a date. If the risk changes later, for example a new supplier or a new system, rescore it and decide again.

The treatment plan and the Statement of Applicability (SoA) should tell the same story.

  • Every control a treatment relies on should be applicable in the SoA.
  • The SoA's reason for including a control often points back to the risks it treats.
  • When a treatment is done, the control's status in the SoA should show it is in place.

An auditor will often pick a high risk, follow it to the treatment, then to the controls in the SoA, then ask for evidence that a control works. Our guide on the Statement of Applicability covers that document in detail.

Keeping the plan moving

The common failure is not a bad plan. It is a plan that stops moving after the first month.

  1. Look at overdue actions every month. Ten minutes in a team meeting is enough. Move a date only with a reason.
  2. Close on evidence, not intent. An action is done when the control works and you have a record that shows it, such as a screenshot of the setting or a restore test log.
  3. Rescore when an action closes. The register should show the result of the work.
  4. Take the status to management review. Put progress on risk treatment on the agenda each time, so that management sees what has moved and what has not.
  5. Treat a missed treatment as a finding. If an action slips badly, raise it as a nonconformity with a corrective action. See our guide on nonconformities and corrective actions.

What an auditor looks for

  • Every risk above the acceptance level has a treatment, or a recorded decision to accept it.
  • Each action has an owner and a date, and there is progress, not only a plan.
  • Residual risk is scored and accepted by the risk owner.
  • The controls in the plan are applicable in the SoA.
  • Evidence that a sample of treatments actually works.

Typical findings: plans with dates that passed months ago, residual risk that nobody accepted, and treatments marked done when the control was only partly in place.

Example: Larkspur Veterinary Group (fictional)

Larkspur is a fictional group of six vet practices. Its first risk assessment found 9 risks above its acceptance level of 10. The practice manager wrote 14 actions, each with one owner and a date, spread over four months. Multi-factor sign-in for the practice management system was one action linked to three risks.

Two risks were accepted. The highest, a ransomware attack on the shared drive, was reduced by moving files to a cloud service with version history and running a quarterly restore test. Its residual score fell to 6 and the IT lead, as risk owner, accepted it. One action slipped by six weeks; it went to the monthly meeting, got a new date and a reason, and closed before the audit.

Questions people ask

Is the risk treatment plan a separate document? It does not have to be. Many teams keep the treatment on the same record as the risk, as long as the plan, owners, dates and residual risk are easy to show.

How many risks should we treat? Those above your acceptance level. The number depends on your method, not on a target.

Can the ISMS lead accept every risk? Only the risks they own. Each risk owner accepts their own risks.

How often should we review the plan? Overdue actions monthly, the whole plan at least once a year and whenever something big changes.

How ClearIMS helps

ClearIMS drafts risk treatments as part of the first draft of your ISMS. People review and approve them. Each action can have an owner and a date, and ClearIMS emails people about their outstanding and overdue actions. They can reply in plain text and ClearIMS updates the action.

Only a risk's owner can accept it, as a step separate from editing. At or above your acceptance threshold it needs a written justification and top-management sign-off. If the score changes later, acceptance resets to Open. Every approval records who approved it, which version and when. The AI never approves anything. We make the software. Your certification is yours, awarded by your certification body.

The price is £300 a month, monthly with 30 days' notice, unlimited users and no VAT charged. Related reading: risk assessment for a small business, the Statement of Applicability explained and nonconformities and corrective actions for a small team.

Book a 20-minute call or try the demo company to see it working first.

SOURCES

  1. ISO/IEC 27001:2022 (ISO)
  2. ISO/IEC 27005:2022, information security risk management guidance (ISO)
SEE IT FIRST

Look round a running ISMS. Then £300 a month.

Enter your work email to explore our demo company, an invented business with its ISMS fully set up. When you’re ready to start for real, it’s £300 a month, billed monthly, and you can cancel with 30 days’ notice. No VAT charged. Need a hand getting set up? Optional setup consulting from SW Digital Services is £500 to £700 a day, quoted per job.

Try the demo companyBook a 20-minute callWe make the software. Your certification is yours, awarded by your certification body.